Database

 

Substations

One must first define, configure, and put on-line one or more substations.

 

Schedules

The next step is to define schedules. Each schedule needs to be defined, configured, and put on-line.

 

Feeders

To build a list of substation feeders one needs to define each feeder, configure it, and put it on-line by adding it to that substation.

Each feeder must be mapped to appropriate analog points to be able to import demand and reactive power numbers from RUEX. This can be done by appropriately specifying RUEX domain, remote unit, demand analog point, and reactive power analog point identifiers.

 

Capacitors

To build a list of feeder capacitors one needs to define each capacitor, configure it, and put it on-line by adding it to that feeder.

Each capacitor must be mapped to a control point, which can be done by appropriately specifying RUEX domain, remote unit, and control point identifiers.

Since capacitor banks can be damaged if reconnected too soon after they have been disconnected from their feeders, respective control point safety timers must be defined appropriately. This makes CCEX not reconnect the banks for at least the specified amounts of time.

Each capacitor must also be mapped to a schedule (see above).

 

Data Processing

RUEX analog point thresholds must be defined (high threshold must be larger than low threshold),  otherwise CCEX does not accept analog point values as valid. CCEX also rejects any values outside the range defined by the thresholds.

Each feeder must be configured to either contribute its values to the owner substation or not. 

Each substation must be configured to either contribute its values to the system total or not. 

 

Data Recording

To record system total data (demand, reactive power, and power factor, one must enable CCEX NTMCRDR.

To record substation data, one must enable substation NTMCRDR.

To record feeder data, one must enable feeder NTMCRDR.

To record capacitor bank activity, one must enable corresponding RUEX control point NTMCRDR. In addition, RUEX records control point activity into RUEX event log file. See documentation on RUEX Control Point Operation Logging parameter. On the CCEX  side, capacitor operation logs can be enabled, however they provide record of capacitor operation requests to RUEX only. The latter actually performs requested operations so RUEX log should be consulted for verification of actual control point operations.

To generate system total management cycle logs, one must enable Management Cycle Logs parameter.

To generate substation management cycle logs, one must enable substation Management Cycle Logs parameter.

To generate feeder management cycle logs, one must enable feeder Management Cycle Logs parameter.

 

Data Archiving

One has to periodically archive data and event logs. Both operations are manually initiated by the operator.

Data archiving is initiated by executing the CCEX Archive Data Recording Files command. The accumulating data files get appended to the corresponding archives located in the NTMCRDR archive directory.

Event log archiving is initiated by executing the CCEX Archive Event Log File command. The accumulating event log file gets copied to the NTMC event log archive directory, common to all NTMC components, and reset to empty.

Data recording files and event log file can be periodically archived automatically if so desired. Care must be taken that archive directory is always available and in the same place, otherwise archives are scattered in different locations, and historical searches become inconvenient.

 

Capacitor Control

In all cases:

  1. Capacitor control must be enabled.
  2. Management method must be defined.
  3. Control parameter must be defined.
  4. Global weekday management must be enabled on the day of the week management is to be performed.
  5. Global start and stop management times of day must be defined properly. In order to be effective, any lower level start and stop times (such as schedules) must be at least as restrictive, or more restrictive than the global start and stop times mentioned above. 
  6. CCEX management period must be defined.
  7. Demand and reactive power units of measure must be defined consistent with physical quantities imported from RUEX.
  8. All substation managers involved in automatic capacitor control must be enabled.
  9. All feeder managers involved in automatic capacitor control must be enabled.
  10. Feeder managers may have to have connect and disconnect priorities properly defined.
  11. All capacitor managers involved in automatic capacitor control must be enabled.
  12. All capacitor managers involved in automatic capacitor control must heave Operation Mode set to Auto.
  13. All capacitors must have Reactive Power Rating properly defined, and greater than zero.
  14. All capacitors must have connect and disconnect priorities properly defined.
  15. All schedule managers involved in automatic capacitor control should be enabled.
  16. Schedule weekday management must be enabled on the day of the week management is to be performed.
  17. Schedule start and stop management times of day must be specified. Care must be taken that these times fully overlap with, and are  at least as restrictive as, or are more restrictive than global management start and stop times of day.
  18. All other schedule parameters must be properly defined in all cases.

 

Global Management

  1. CCEX Management Method parameter must be set to Global.
  2. CCEX Connect and Disconnect thresholds must be defined in units consistent with the value of the Control Parameter. For example, if the latter is set to Reactive Power, the thresholds must be specified in terms of VArs.
  3. All substations involved in global management must have Contribution to Global parameter Enabled.

 

Management By Substations

  1. CCEX Management Method parameter must be set to By Substations.
  2. Substation Connect and Disconnect thresholds must be defined in units consistent with the value of the Control Parameter. For example, if the latter is set to Reactive Power, the thresholds must be specified in terms of VArs.
  3. Feeder Contribution to Substation parameter must be Enabled.

 

Management By Feeders

  1. CCEX Management Method parameter must be set to By Feeders.
  2. Feeder Connect and Disconnect thresholds must be defined in units consistent with the value of the Control Parameter. For example, if the latter is set to Reactive Power, the thresholds must be specified in terms of VArs.

 

Capacitor State Reinserting

For Capacitor State Reinserting to work, CSR manager must be Enabled, and Reinserting Period must be defined.

 

        [ Contact Us]  [Terms of Service]  [Privacy Statement]  [Customer References]  [Top of Page]

This web site developed and managed by BTE Corporation.
Copyright © 1998 - 2012, BTE Corporation, All Rights Reserved
Equal Employment Opportunity Statement